Loughborough University, Leicestershire

Share:
Loughborough University Leicestershire external

Project details

51.25m x 20m pool with movable floor and traversable boom.

Project role

Water treatment, moveable floor and traversable boom.

Prior to the design of the traversable boom at Loughborough University, booms had been installed in the UK that had taken up to 30 minutes to move 25m. A brief for the traversable boom was agreed that the movement time should be a maximum time of 15 minutes. In order to achieve this a number of specific design criteria were incorporated into the system, including:

  • a high level of perforation of both sides of the boom
  • opening gates at either end of the boom
  • elevation of the boom off the floor by approximately 200mm during movement
  • dropping of the movable floor under the boom to provide for increased water flow area

The commissioning of the boom demonstrated that the traversable boom could be moved a distance of 25m in a time as short as 8 minutes.

The water treatment system is specifically designed to cater for the bather loads planned for this centre of excellence – this has resulted in lower capital and lower operating costs.

If you would like to learn more about what we can do for your next project, please visit our Services page.

  • Client:

    Loughborough University

  • Completion:

    2002

  • Architects:

    FaulknerBrowns

  • M&E Engineers:

    Max Fordham

  • Pool Consultant:

    Devin Consulting