+44 (0)191 258 1653
 

University of Surrey

Client:

University of Surrey

Completion:

2010

Construction Costs:

£27,100,000


Project Details:

A 50m x 21m pool with a movable floor and traversable boom.

Our Role:

Design of the water treatment, movable floor and traversable boom; site monitoring of installation and commissioning.


Design Team

Architects:

FaulknerBrowns

Main Contractor:

Northcroft

Structural Engineer:

SKM Anthony Hunt

M & E Engineers:

Hoare Lea


Further description

 

The brief for the movable floor – to move 25m in 15 minutes or less – was achieved by careful considerations to the boom perforations, elevation and opening end gates.

The water treatment plant was designed to provide an excellent water quality, for high level competitive swimming.