+44 (0)191 258 1653
 

Kirkcaldy Leisure Centre, Fife

Client:

Fife Council

Completion:

2013

Construction Costs:

£15M


Project Details:

16.67m x 8m training pool with an underwater movable floor, 25m six-lane swimming pool. Health suite with sauna and steam room.

Our Role:

Design and specification of the pool water treatment and movable floor; site monitoring of installation and commissioning.


Design Team

Architects:

B3 & Cre8architecture

Main Contractor:

Graham Construction

Quantity Surveyor:

Turner Townsend

Structural Engineer:

Arup

M & E Engineers:

Arup

pool consultant:

Devin


Further description

Independent water treatment plants are provided for each of the pools. This facilitates independent temperature control in each pool.

Circulation within the training pool takes account of the movable floor.

The water treatment system incorporates PAC flocculation, medium rate filtration on sand, photo-oxidation using ultraviolet, heating, pH control and residual disinfectant control using chlorine. VSDs control pump flows linked to an electronic flow meter. Full area movable floor in training pool provides a range of water depths for different training activities.